Tahura Djuanda toilets at Rp118.5 million go viral, still unpaid

The two toilets in the Tahura Djuanda forest park are unpaid and will be reviewed by the Inspectorate. Managers say the budget covers sanitation and piping.

What

The construction of two public toilets in Taman Hutan Raya (Tahura) Ir H Djuanda, a forest park in Bandung, has drawn heavy discussion on social media because of its budget. According to project data from the West Java Provincial Forestry Office, through its Tahura technical unit (UPTD), the work is at Cadas Bugis and Curug Ciomas, with a budget of Rp120 million including tax.

That figure is the owner's estimate price, known in Indonesian as Harga Perkiraan Sendiri (HPS). The value in the contract is recorded at Rp118.5 million including tax. The UPTD Tahura manager confirmed that the project has not been paid to the contractor.

The work is scheduled to run for one month, from November 12 to December 11, 2026. Construction is still under way and has not reached the payment stage.

Why

The head of UPTD Tahura said the Rp120 million figure is not fixed. After negotiation, the value came down to about Rp118,500,000.

According to Lutfi, the budget was not spent entirely on the physical building. It also covers supporting components such as toilet fixtures, urinals, sinks, a biofil sanitation system, and piping. The project planner explained that the specifications also include structural work, including foundations. The distance for moving materials is said to range from one to four kilometers, and it is included in the cost budget calculation.

The second location is in the middle of the forest and fairly far from the main entrance. Four-wheeled vehicles cannot reach it, so transporting materials needs special handling.

What's next

West Java Governor Dedi Mulyadi said the project has not been paid. "If the project is poor and does not match the value of the money, then we will not pay," Dedi told the news site detik (translated from Indonesian). He also asked the UPTD finance section to confirm the payment status and hold payment until the value of the work is audited.

On the manager's side, Lutfi said that after the handover there will be assistance and an inspection. The result will decide whether payment is made in full or "according to the calculations from our colleagues at the Inspectorate," the government's internal auditor. The assistance means measuring the quality and quantity of the work before payment. The UPTD also said the work will be evaluated and inspected under the rules before any payment is made.

Under the contract, the work is due to finish no later than December 11, 2026.