100 GWp solar plan needs Rp1,140 trillion: who pays, why investors balk
The government wants 100 GWp of solar installed by 2029. Here is how PLN, Danantara and private firms split the work, and what lenders want in contracts.

The short version
The government is targeting national installed solar power capacity of 100 gigawatts by 2029. To build it in three years, Katadata, an Indonesian business news outlet, puts the investment need at about US$71.3 billion, equal to Rp1,140 trillion. Danantara, the sovereign wealth fund, gave a slightly different figure on August 26, 2026: about Rp1,130 trillion.
The money is not meant to come from a single source. The government is opening the door to private investors through the Independent Power Producer (IPP) scheme, in which a private company builds a plant and sells the electricity, with Danantara as one option if no competitive investment offers emerge. According to Jisman P Hutajulu, a senior adviser to the energy minister, Danantara can help with financing, local governments provide land, and PLN (Perusahaan Listrik Negara), the state electricity company, acts as the power buyer and auctions projects once the land is ready.
Investor doubts center on certainty. Standard Chartered Indonesia says investment will only materialize if the government provides certainty on power purchase contracts, tariffs, risk sharing, permits and land access. The Institute for Essential Services Reform (IESR), an energy think tank, says current power purchase contracts do not balance risk between developers and the buyer, which makes it hard for many solar projects to get commercial bank loans. Meanwhile, the presidential regulation that will serve as the legal basis for the program was still being harmonized among ministries as of September 16, 2026.
How did the 100 GWp solar plan get here?
The starting point is the RUPTL (Rencana Usaha Penyediaan Tenaga Listrik), PLN's electricity supply business plan, which lists the power plants to be built. The 2025-2034 RUPTL was approved on May 26, 2025, through Energy and Mineral Resources Ministry Decree, coded Tenaga Listrik (TL) and Menteri Energi dan Sumber Daya Mineral (MEM), No. 188.K/TL.03/MEM.L/2025. The energy minister later said he would instruct PLN to speed up construction of new plants already approved in the RUPTL.
The Energy and Mineral Resources Ministry then presented a plan to accelerate solar at large scale. The deputy minister said (translated from Indonesian), "We will start the acceleration by building 17 gigawatts first". That first phase comes with battery energy storage systems (BESS) of about 33 gigawatts. After coordinating with the Agrarian Affairs and Spatial Planning/National Land Agency Ministry, the ministry identified about 24,000 hectares of land on Java that could potentially be used.
President Prabowo Subianto then gave a faster timeline. In Karawang on July 9, 2026, he said, "This year PLN will start [building solar plants] with 17 gigawatts this year; 100 gigawatts in two years". On July 28, 2026, at the State Palace, Energy Minister Bahlil Lahadalia said, "We also discussed the implementation of the 100 gigawatt solar program, which God willing will soon be marked by the first groundbreaking".
Acting Director General of Electricity Tri Winarno then confirmed the target is already in the revised RUPTL, saying, "100 GW is already in (the RUPTL revision), peak, mind you, 100 GWp". The unit he stressed, GWp or gigawatt peak, refers to the peak capacity of solar panels. Bahlil also said he was trying to find a slot in the President's schedule to inaugurate the first phase.
The first project was launched on August 25, 2026, in Gilimanuk, Bali, as a solar plant with BESS. A day later, on August 26, 2026, Danantara announced its estimate of an investment need of Rp1,130 trillion. On September 3, 2026, Jisman said the presidential regulation was still under discussion, and on September 16, 2026, Farah Heliantina, an assistant deputy at the Coordinating Ministry for Economic Affairs, said it was being harmonized with ministries and agencies.

Who builds, who buys the power, and who pays?
The rules of the program will be set out in a presidential regulation that the government is drafting as the legal basis for the 100 GWp solar plan. That regulation may also create a dedicated body to handle the program.
Not all of the 100 GWp goes into PLN's plan. The government breaks it down as 54.7 GWp in the RUPTL, 15.3 GWp for rooftop and non-rooftop solar, and 30 GWp aimed at creating new demand from industry. That means only a little more than half of the target will be planned through PLN's document, while the rest depends on installations outside PLN's planning and on new buyers emerging.
For the portion inside the RUPTL, PLN has two roles. First, PLN is tasked with speeding up construction of plants already approved in the RUPTL, and the President said PLN will start building the first 17 gigawatts. Second, PLN is the offtaker, or power buyer, and Jisman said, "PLN as the offtaker will find it easy to auction that," once land is ready.
In Jisman's outline, the sequence starts with land provided by local governments, then financing that Danantara can help with. PLN then auctions the project as the electricity buyer. Private firms can enter as IPPs, while Danantara is an option if no competitive investment offers appear.
The relationship between developers and PLN is bound by a power purchase agreement (PPA), known in Indonesian as PJBL (Perjanjian Jual Beli Listrik). This contract sets out who bears which risks between the developer and the single buyer. IESR recommends speeding up procurement through competitive, transparent and bankable auctions, meaning projects that banks can finance, so that electricity prices are competitive.
The 100 GWp target: 54.7 GWp enters the RUPTL, the rest sits outside PLN's plan
GWp
- Included in RUPTL 54.7 54.7 GWp of the 100 GWp target will enter the RUPTL.
- New industrial demand 30
- Rooftop and non-rooftop solar 15.3
View data
| Included in RUPTL | 54.7 GWp |
|---|---|
| New industrial demand | 30 GWp |
| Rooftop and non-rooftop solar | 15.3 GWp |
How big are the numbers compared with what exists?
Two figures for the investment need are circulating. Katadata wrote US$71.3 billion, or Rp1,140 trillion, to build 100 GWp in three years. Danantara, on August 26, 2026, gave about Rp1,130 trillion. The gap is Rp10 trillion.
For comparison, actual energy investment in 2025 was far smaller. The Energy and Mineral Resources Ministry recorded US$4.6 billion in the electricity subsector and US$2.4 billion in the new, renewable energy and energy conservation (EBTKE) subsector during 2025. If the US$71.3 billion need is spread evenly over three years, the result is about US$23.8 billion a year, nearly ten times the 2025 EBTKE investment.
Installed capacity is also still small. At the end of 2025, renewable generation capacity stood at 7,587 MW for hydro, 3,148 MW for bioenergy, 2,744 MW for geothermal and 1,494 MW for solar. The 1,494 MW of solar is about 1.5 gigawatts, against a target of 100 GWp by 2029.
On resources, the target is considered realistic. IESR estimates Indonesia's technical solar potential at 3,000 to 7,000 GWp, so a 100 GWp target is considered feasible. Technical potential is the capacity that could technically be built, not what already exists.
The first project gives a sense of the physical scale. The Gilimanuk solar plant in Bali has a capacity of 198 MWp with 666 MWh of BESS on about 211 hectares, and is targeted to operate in 2028. Its 198 MWp is about 0.2 percent of the 100 GWp target. For the first phase, the land identified on Java is about 24,000 hectares.
Installed solar capacity is only 1,494 MW, the smallest of four renewable sources
MW
- Hydro 7,587
- Bioenergy 3,148
- Geothermal 2,744
- Solar 1,494 Solar generation capacity stood at 1,494 MW at the end of 2025.
View data
| Hydro | 7,587 MW |
|---|---|
| Bioenergy | 3,148 MW |
| Geothermal | 2,744 MW |
| Solar | 1,494 MW |
What do the parties say?
The government presents the program as an accelerated priority. The Energy and Mineral Resources Ministry states a target of 100 GW installed by 2029, while the President speaks of 100 gigawatts in two years. Katadata notes the program is targeted for completion in roughly three years, in 2029, the final year of the Prabowo administration.
Danantara casts itself as a provider of capital. Pahala, of Danantara, explained that the agency can act as an equity investor, meaning an investor that takes an ownership stake, in financing green economy projects. That role, he said, is backed by the issuance of Patriot Bonds, which lets Danantara develop sustainable financing schemes under a blended financing concept.
The coordinating ministry is still finishing the rules. Farah Heliantina of the Coordinating Ministry for Economic Affairs said, "It is being discussed, we are harmonizing (with ministries/agencies)". Jisman of the Energy and Mineral Resources Ministry called it a "new presidential regulation that is still under discussion".
IESR focuses on execution. IESR CEO Fabby Tumiwa said, "The biggest challenge now is turning the President's political commitment into an implementation machine capable of building tens of gigawatts of solar every year". IESR also says the government needs to quickly name who leads the program, with authority to coordinate across ministries and financing institutions, including PLN.
IESR even proposes a form for that body. According to IESR, "A National Energy Transition Task Force or Special Coordinating Body is needed, directly under the President's leadership" to overcome siloed coordination among ministries. The proposal is in line with the dedicated body that the presidential regulation may establish.

Why are investors still hesitant?
For lenders, the main issue is long-term certainty. Standard Chartered Indonesia says investors need government certainty on power purchase contracts, tariffs, risk sharing, permits and land access. Adhi Sulistyo Wibowo of Standard Chartered explained, "The longer the contract, the longer the financing, the higher the level of certainty the financiers expect".
The first source of doubt is the power purchase contract. IESR says the PJBL or PPA scheme does not yet balance risk between developers and PLN as the single buyer, so many solar projects struggle to get commercial bank financing. IESR proposes, "The government and PLN need to revise the PPA scheme to align with fair international standards [bankable PPA]".
The second is the kind of loans available at home. According to IESR, domestic banks generally offer only short-term loans at relatively high interest rates. Yet power plants are financed with long contracts, and lenders demand ever higher certainty for ever longer financing.
The third is layered regulation. IESR says, "The regulatory keys are clear, there should be no need to keep fiddling with this regulation and that regulation". Until the presidential regulation is issued, that regulatory certainty is not available, because the draft is still being harmonized.
The fourth is the market. Systemiq says investors weigh market prospects and cash flow, and states, "Building the market, or demand, is extremely important". The government itself has set aside 30 GWp of the target to create new demand from industry.
As a way out on financing, IESR suggests mixing funding sources, including the Just Energy Transition Partnership (JETP). According to IESR, "The blended finance scheme [a mix of grants, soft loans and private capital] can be optimized by using global facilities such as the Just Energy Transition Partnership [JETP] and Climate Investment Funds". Danantara also cites the blended financing concept as part of its role through the Patriot Bond.
What happens next?
The nearest decision point is the issuance of the presidential regulation. As of September 16, 2026, it was still being harmonized with ministries and agencies. This regulation is the one that may set up a dedicated body responsible for the program.
The second is PLN's planning document. Tri Winarno says 100 GWp is already in the revised RUPTL. The base document already approved is the 2025-2034 RUPTL, set on May 26, 2025. Under the government's breakdown, the portion going into the RUPTL is 54.7 GWp.
On the ground, the first phase begins with 17 gigawatts. Bahlil says he is trying to find a slot in the President's schedule to inaugurate that first phase. The Gilimanuk project, launched on August 25, 2026, is targeted to operate in 2028.
The final deadline is 2029, about three years from now. The President has named a faster target, 100 gigawatts in two years. To meet the deadline, IESR says what is needed is an implementation machine able to build tens of gigawatts each year.
What this means for readers
For taxpayers and owners of public funds, how big a role the state plays depends on private interest. Danantara is described as a financing option if no competitive investment offers come from private firms. Danantara says it can come in as an equity investor, backed by the issuance of Patriot Bonds.
For residents near project sites, the program involves large amounts of land. Local governments are said to be the ones providing it. On Java alone, about 24,000 hectares have been identified as potentially usable, and a single 198 MWp project in Gilimanuk needs about 211 hectares.
For households and businesses, there is a share outside the large power plants. A total of 15.3 GWp of the target is aimed at rooftop and non-rooftop solar. For industry, 30 GWp is aimed at creating new demand.
For electricity customers, the price still depends on how projects are procured. IESR recommends competitive, transparent and bankable auctions to produce competitive electricity prices.
Ultimately, whether the 100 GWp target succeeds hinges on the same things that make lenders hesitate. Standard Chartered names contracts, tariffs, risk sharing, permits and land as the conditions for certainty. Until those points are settled, the Rp1,140 trillion required remains an estimate of need, not a financing commitment.
Sources: Kementerian ESDM
- Ujung Pangkal
MUI fatwa 131/2026 on vapes: how binding it is, and why cigarettes differ
A fatwa banning vapes is not automatically state law. Here is the path it must take, why vapes differ from cigarettes, and what rules apply now.
Ujung Pangkal PSSI chair election limited to two candidate slates: how it works
A rule requiring 35 endorsements per slate from 85 voters limits the PSSI chair election to two slates. Here is how it works and what it changes.