PLN's chief ties his 2034 target to the RUPTL, while the energy ministry names 2032 for the first plant. The government has yet to decide on building it.

Deputy Minister of Energy and Mineral Resources Yuliot delivers the keynote at the BAPETEN Executive Meeting and BAPETEN Award 2025 in Jakarta on Monday, 27 October 2025.
Deputy Minister of Energy and Mineral Resources Yuliot delivers the keynote at the BAPETEN Executive Meeting and BAPETEN Award 2025 in Jakarta on Monday, 27 October 2025. · Photo: Kementerian ESDM

What

PLN, the state electricity company, is preparing to buy all the power from a nuclear power plant that is targeted to start operating in 2034, CNBC Indonesia reported. PLN President Director Suroso Isnandar stated the company's position at the St. Regis in Jakarta on Wednesday, Nov. 25, 2026, according to Detik.

"So we are only waiting for direction from the government. This is just our preparation, especially PLN's position as the offtaker. That means what matters is that it produces electricity, and we buy the electricity. We are ready to absorb 100%," Suroso said, as quoted by Detik (translated from Indonesian). With that statement, PLN set itself up as the buyer of the electricity the plant produces.

Suroso also mentioned 21 candidate sites for a nuclear plant that the National Research and Innovation Agency (BRIN), or the former National Nuclear Energy Agency (BATAN), had studied earlier, according to CNBC Indonesia.

Why

Suroso linked the 2034 target to the RUPTL, PLN's long-term electricity supply business plan. "In line with the plan in the RUPTL, by 2034 we hope it will already be there, in line with the RUPTL plan," he said, according to CNBC Indonesia.

A press release from the Energy and Mineral Resources Ministry on PLN's 2025-2034 RUPTL lists the construction of two small reactor units in Sumatra and Kalimantan, each with a capacity of 250 MW. The two units add up to 500 MW, the same figure that Deputy Energy and Mineral Resources Minister Yuliot Tanjung cited on Oct. 22, 2026. "Actually, in our RUPTL, in 2032-2034 we will have at least 500 MW on-grid," Yuliot said, according to CNBC Indonesia.

Officials have not named the same target year. In October 2025, the ministry relayed a statement from the deputy minister that national policy documents, including the National Energy Policy, confirm a commitment to operate the first nuclear power plant in 2032 and reach a capacity of 44 GW by 2060. The targets in circulation therefore range from 2032 in the national policy documents, to a 2032-2034 window according to Yuliot, to 2034 according to PLN's chief.

What's next

PLN is still waiting for a government decision on plans to build a nuclear power plant, according to Detik. Suroso himself described PLN's current steps as preparation only while it waits for direction from the government.

For developers, the 2025-2034 RUPTL plans for about 73 percent of total generating capacity to come from partnerships with private companies, known as Independent Power Producers (IPPs), with the rest run by the PLN Group. PLN made its commitment to buy all the electricity from a nuclear plant within the framework of that plan.

On costs, the Energy and Mineral Resources Ministry estimates that investment in a single nuclear unit could reach USD3.8 billion, with construction taking about four to five years. That figure is one of the factors in the economics of a project whose electricity PLN would eventually buy.