Private firms get priority under an IPP scheme, with Danantara as a fallback. The RUPTL revision and a presidential regulation were pending in September 2026.

Energy and Mineral Resources Minister Bahlil Lahadalia announced PLN's 2025-2034 electricity supply business plan (RUPTL) at a press conference in Jakarta, Monday, 26 May 2025.
Energy and Mineral Resources Minister Bahlil Lahadalia announced PLN's 2025-2034 electricity supply business plan (RUPTL) at a press conference in Jakarta, Monday, 26 May 2025. · Photo: Kementerian ESDM

What

The government says its 100 GWp solar power program (known as Pembangkit Listrik Tenaga Surya (PLTS)) will require about Rp1,140 trillion in investment, a figure given by Energy and Mineral Resources Minister Bahlil Lahadalia. Media outlets differ on the dollar equivalent: about US$73 billion according to Katadata and about US$71.3 billion according to Kontan.

President Prabowo Subianto said, "We will build 100 gigawatts and we are not joking around, our target is 100 gigawatts in three years" (translated from Indonesian), according to a press release from the Energy and Mineral Resources Ministry. Katadata reported that Prabowo also envisions the projects being finished in two years if the relevant ministries and agencies work to target. The government itself calls 100 GWp the maximum target to be reached.

For comparison, Prabowo said Indonesia's entire electricity capacity today is about 88 gigawatts from all types of power plants. The first phase consists of 14 solar projects in six provinces with a combined capacity of about 5.3 GWp, according to the ministry. A government fact sheet puts the capacity of those 14 projects at about 5.2 GWp, with an investment value of about Rp135 trillion.

Why

According to the government fact sheet, the Rp1,140 trillion will go to solar development nationwide, replacing diesel power plants, rural electrification and productive villages, strengthening the power grid, and developing industrial estates. To make this happen, the government will give priority to private business entities through an Independent Power Producer (IPP) scheme.

If no investors are interested or the prices offered are not competitive, the government is open to taking over the work through Danantara, the sovereign wealth fund. Bahlil said the projects would be carried out by the government through Danantara "with financing in line with the President's instructions," as quoted by Kontan.

The program is also tied to budget savings. According to the minister's report, it could save the state budget more than Rp73 trillion a year because solar electricity costs less than power from diesel or gas plants. That calculation compares solar power paired with battery energy storage systems (BESS) against electricity from gas-steam and diesel plants.

For comparison, in the 2025-2034 electricity supply business plan (RUPTL) of Perusahaan Listrik Negara (PLN), the state electricity company, about 73 percent of planned generation capacity is to come through partnerships with the private sector, or IPPs, while the rest is handled by the PLN Group.

What's next

The Energy and Mineral Resources Ministry says it will revise PLN's 2025-2034 RUPTL to support the program. Harris, secretary of the ministry's Directorate General of New and Renewable Energy and Energy Conservation (EBTKE), explained that any power plant connected to the grid must be planned in the RUPTL, so the 100 GW of solar will be added to it. The 2025-2034 RUPTL announced earlier includes 17.1 GW of solar power.

On September 22, 2026, Bahlil said a revision is certain because "it is impossible for a program to run without rules to base it on". Tri Winarno, acting Director General of Electricity, said the process is under way. The target is to finish it this year.

The government is also preparing a presidential regulation as the legal basis for developing solar power of up to 100 GWp. As of September 8, 2026, the draft was still being discussed across ministries and agencies.

The grid is a concern in its own right. Bahlil has said that if power plants are built without a grid, PLN must bear a take-or-pay obligation of 80 percent. Deputy Energy and Mineral Resources Minister Yuliot said PLN's transmission lines and substations will be connected to plants on 24 thousand hectares of land on Java that the ministry has prepared together with the Agrarian and Spatial Planning Ministry/National Land Agency (ATR/BPN).